VIETNAM – THE GOVERNMENT REQUESTS MOIT TO CLARIFY POINTS ON DRAFT PDP 8 BEFORE FINALIZATION

Oliver Massmann by Oliver Massmann
April 10, 2023
in Article
0
403
SHARES
2.4k
VIEWS
Share on FacebookShare on Twitter

On 15 July 2022, the Government Office issued Notice No. 206/TB-VPCP, stating the Deputy Prime Minister Le Van Thanh’s respond to MOIT’s Official Letter No. 3787/BCT-DL. Please find our legal alert on Letter 3787: https://blogs.duanemorris.com/vietnam/2022/07/12/vietnam-moit-proposes-new-mechanism-to-develop-solar-and-lng-power-projects/

 

Under Notice 206, Deputy Prime Minister Le Van Thanh asked MOIT to clarify the following points:

 

  1. MOIT to clarify the legal basis to remove coal projects already approved in (revised) PDP 7 from the PDP 8

 

  1. MOIT to clarify and estimate the cost, damage due to suspension, suitability of 2,428,42 MW solar power projects which MOIT proposed to add into PDPVIII

The inclusion of 2,428,42 MW of solar capacity into the draft PDP 8 must be divided into:

 

(i) Projects that completed construction;

(ii) Projects that have been granted land and sign contracts for purchase of equipment;

(iii) Projects that obtained Decision on Investment Policy and granted land; and

(iv) Projects that obtained Decision on Investment Policy but has not been granted land.

 

It is necessary to determine in general the costs and damages for each group of projects mentioned above if they are not put into operation, clearly analyze the suitability and non-conformity of each project in accordance with the provisions of law.

 

  1. MOIT to clarify and explain why not obtaining the Politburo’s opinion regarding LNG projects under Resolution 55 – NQ/TW dated 11 Feb 2020 in relation to capacity to import LNG.  Draft PDP 8 proposes 14-18 billion m3 importation by 2030 and 146,000 MW by 2030 while Resolution 55 only allows 8 billion m3 by 2030 and 15 billion m3 by 2045 and capacity of 125,000-130,000 GW by 2030.

 

DPM required the MOIT to report prior to 21 July 2022.

 

Please do not hesitate to contact Dr. Oliver Massmann under [email protected] if you have any questions or want to know more details on the above. Dr. Oliver Massmann is the General Director of Duane Morris Vietnam LLC.

 

 

 

Previous Post

VIETNAM – SEMICONDUCTOR PRODUCTION INDUSTRY – BEST PLACE FOR INVESTMENT

Next Post

VIETNAM – THE NEXT WORLD’s FACTORY? – Lawyer in Vietnam Dr. Oliver Massmann in interview with Caijing Magazine Beijing

Next Post
VIETNAM – FINANCIAL TIMES INTERVIEW WITH DR. OLIVER MASSMANN ON NEW GOVERNMENT POLICIES ON NEW FEED IN TARIFFS FOR SOLAR AND WIND AND NEW WODEL STANDARD PPAs FOR RENEWABLE ENERGY SECTOR

VIETNAM - THE NEXT WORLD’s FACTORY? - Lawyer in Vietnam Dr. Oliver Massmann in interview with Caijing Magazine Beijing

Contact

Dr. Oliver Massmann can be reached under [email protected]

Recent Posts

  • Über die WTO-Compliance hinaus: Warum Vietnam ein Genehmigungsfiktion‑Verfahren für verbindliche Zollauskünfte einführen sollte – Lernen von internationalen Best Practices zur Schaffung der nächsten Generation der Handelserleichterung
  • Vietnam’s Consumer Revolution: A Strategic Opportunity for German Retail
  • Vượt ra ngoài tuân thủ WTO: Vì sao Việt Nam nên áp dụng cơ chế “được coi là phê duyệt” đối với các quyết định trước về hải quan
  • Beyond WTO Compliance: Why Vietnam Should Introduce a Deemed Approval Mechanism for Advance Customs Rulings
  • Vietnam Opens the Door to a New Wave of Energy Investment: Decree 272 Creates Major Opportunities for Foreign Investors

About Us

Dr. Oliver Massmann is an International Attorney at Law and a Financial Accountant and Auditor.

Dr. Massmann received his PhD with Major in International Business Law.

Dr. Massmann has over 20 years experience working as commercial lawyer in Vietnam. Dr. Massmann is fluent in Vietnamese language, negotiation and presentation level.

Contact

Dr. Oliver Massmann can be reached under [email protected]

Category

Article

News And Regulations

Presentation

Recent Posts

  • Über die WTO-Compliance hinaus: Warum Vietnam ein Genehmigungsfiktion‑Verfahren für verbindliche Zollauskünfte einführen sollte – Lernen von internationalen Best Practices zur Schaffung der nächsten Generation der Handelserleichterung
  • Vietnam’s Consumer Revolution: A Strategic Opportunity for German Retail
  • Vượt ra ngoài tuân thủ WTO: Vì sao Việt Nam nên áp dụng cơ chế “được coi là phê duyệt” đối với các quyết định trước về hải quan

© 2023 Vietnamlaws.xyz

  • Home
  • International Arbitration
  • News and Regulations
  • Presentation
  • Article
  • WORLD BANK CERTIFICATION
  • Deutsch

© 2023 Vietnamlaws.xyz

News
  • Lawyer in Vietnam Dr. Oliver Massmann – The Shipbuilding Sector – INTERVIEW ON PRACTICAL SIGNALS FOR MARITIME DECISION MAKERS IN 2026 (3/20/2026)